JFK T8 Bus Stop

Project Status:

Completed

Scope of Work:

  • Furnish & Install all required drywall partitions and framing per construction documents. This includes and
    is not limited to gypsum walls, gypsum board ceilings, soffits/fascias, window pockets, stud, top and bottom track
  • Furnish & Install all required exterior framing and sheathing per construction documents
  • Install all required hollow metal doors, frames and hardware per construction documents. Doors, Frames and Hardware to be provided by others.
  • Furnish & Install all required corner guards per construction documents.
  • Furnish & Install all required seismic bracing per construction documents
  • Install all required Fire Extinguishers and Fire Extinguisher Cabinets per construction documents. Fire
  • Extinguisher and Fire Extinguisher Cabinet is to be provided by others.

Location:

JFK Airport Terminal 8 Jamaica , NY, 11430

Size:

$680,000

Year:

2024

Architect:

Corgan Associate Architects

Types:

Industrial

Related Projects

Allen Edmonds

Allen Edmonds

Allen EdmondsScope of Work: Wooden Walls and Ceilings, Metal Wall framing, Soffits, Drywall Finishing Location: 30 Rockefeller Center, New York, NY Size: $90,000 - $100,000 Year Completed: 2017 Type: RetailSimilar Projects

read more
The Ark

The Ark

The ArkScope of Work: Drywall, ceilings & soffits, ACT ceilings, cement board ceilings, light guage metal framing, install animal cages Location: JFK Airport Building 78 Size: $1,000,000 - $5,000,000 Year Completed: 2016 Architect: Gensler Type:...

read more
Victoria Secret Flagship Store

Victoria Secret Flagship Store

Victoria Secret Flagship StoreScope of Work: Drywall, ceilings, soffits, install door frames and hardware, OSHA protection, GRG light cove, wall protection, FRP panels, light gauge metal framing, prefabrication of headers and sheetrock with plywood Location: 640 5th...

read more